Lilaravi Enclave, Khagaul: What the RERA File Says About This Grihini Homes Project

Lilaravi Enclave in Khagaul, Patna checked: RERA number, builder Grihini Homes, 50:50 land deal, building permit, prices, complaints and a buyer checklist.

PropertyJasoos casefile card: Lilaravi Enclave, Khagaul
In this guide
  1. 1. The project at a glance
  2. 2. Where exactly is it?
  3. 3. Who is the builder?
  4. 4. Land and approvals
  5. 5. Prices, flat sizes and what the portals claim
  6. 6. Complaints, cases and buyer reviews
  7. 7. Buyer checklist before booking
  8. Sources

We are detectives for property, and we share what we investigate. A reader asked us about “Lilravi Enclave”. The project is registered with Bihar RERA as Lilaravi Enclave, and listing portals call it “Grihini Lilaravi Enclave”. We read its full RERA file, the building permit and the builder’s own declarations. Here is what we found.

Short answer: Lilaravi Enclave is a properly registered, small G+4 building with 32 flats in Badi Khagaul, near Danapur station. We found no RERA complaints, penalties or defaulter listing against it. The main risk is execution: it is the first project of a firm set up in 2022, built on a landowner’s plot under a 50:50 sharing deal, with a deadline of 19 May 2028.

Builder's artist impression of Lilaravi Enclave, a five-storey apartment block with balconies
Artist’s impression by the builder, as shown on the Houssed listing. The real building may differ.

1. The project at a glance

All figures below come from the promoter’s application on the Bihar RERA portal. We also have a Lilaravi Enclave project page.

ItemWhat the RERA file says
RERA numberBRERAP12438-001/122/R-1618/2023
Registered on10 Nov 2023
PromoterGrihini Homes (partnership firm)
LocationMauza Badi Khagaul, Khagaul, Patna (survey plot 1264 part, khata 30, thana 49)
BuildingOne block, ground plus 4 floors, RCC frame
Flats32 (2 BHK and 3 BHK, as per listings)
Plot area1,391.26 sq m (about 0.34 acre)
Total built-up area3,362.51 sq m
Sanctioned FAR2.41
Start date20 May 2023
Completion deadline19 May 2028
Declared costAbout ₹5.07 crore construction plus ₹1.72 crore land
RERA bank accountIDBI Bank, Ashiana branch, Patna
Bar chart of Lilaravi Enclave areas: built-up 3,363 sq m, land 1,391 sq m, covered 801 sq m, open 560 sq m
Chart: PropertyJasoos, from the Bihar RERA filing.

2. Where exactly is it?

The RERA file gives the plot’s coordinates as 25.57195, 85.030758. That puts it in Khagaul, south of the Danapur railway line, about 1.9 km in a straight line from Danapur station and about 6.4 km from Patna airport. The building permit says the plot is reached by an approved road 19.51 m wide.

Some portals list the project under Phulwari Sharif. That label comes from the old revenue name “Pargana Phulwari” in the land records. On the ground, the site is in Khagaul.

Street map of Khagaul, Patna with a red pin at the Lilaravi Enclave RERA coordinates, south of the Danapur railway line
Map: PropertyJasoos. Map data © OpenStreetMap contributors. Pin placed at the coordinates in the RERA file.
Builder's location sketch showing Lilaravi Enclave near Danapur railway station, Khagaul Road and Saguna More
Builder’s location sketch (not to scale), as shown on the Houssed listing.

🔍 Jasoos take: The builder’s location sketch is not to scale. Before you visit, put the RERA coordinates into Google Maps, then check the actual road width, drainage and waterlogging during the monsoon yourself.


3. Who is the builder?

Grihini Homes is a partnership firm registered on 21 February 2022, with its office at Akashwani Road, Khajpura, Patna. Its partners are Pankaj Kumar and Swati Raj Singh. In letters filed with RERA in August 2023, the firm says:

  • Lilaravi Enclave “is our First Project”.
  • The partners have not built any project on their own and are not linked with any other real estate firm.
  • It had no bank account or income tax return for 2021-22. It filed this letter in place of a balance sheet and profit and loss statement.

Search engines often mix up Grihini Homes with Grih Vatika Homes. They are different companies.

🔍 Jasoos take: A first project is not a bad sign by itself, but there is no completed building to inspect and no financial history to judge. That makes site progress and the RERA bank account your main safeguards.


4. Land and approvals

The builder does not own the land. According to its Form B affidavit, the land belongs to a private landowner. The builder develops it under a registered development agreement: deed no. 9339 dated 27 May 2022, registered at the Danapur sub-registry office, with a 50:50 share of flats.

Approval or documentDetails
Development agreementDeed 9339, 27 May 2022, Danapur sub-registry, 50:50 sharing
Building planNagar Parishad Khagaul, letter no. 670 dated 20 May 2023, G+4 residential (applied 16 Dec 2022)
Plan validity5 years from issue, so until about May 2028
Parking condition714.53 sq m of parking must stay open, with no construction on it
Title conditionThe permit is not proof of title, and it is treated as cancelled for as long as any land-record dispute lasts
Airport (AAI) and environment (SEIAA) NOCsThe builder declared that neither is needed for this size and location
Diagram of 32 flats over four floors: builder owns flats 201 to 208 and 301 to 308, the rest are the landowner share
Chart: PropertyJasoos, from the builder’s flat-sharing declaration in the Bihar RERA filing.

🔍 Jasoos take: The builder’s notarised declaration lists its 16 flats as 201 to 208 and 301 to 308. If you are offered any other flat, it comes from the landowner’s share. Ask who will sign your agreement and sale deed, and make sure both the landowner and the builder are bound by it.


5. Prices, flat sizes and what the portals claim

Lilaravi Enclave does not appear to have its own website. On Houssed, the asking prices are:

TypeSuper built-up areaAsking pricePer sq ft (our calculation)
2 BHK1,147 sq ft₹86.02 lakhabout ₹7,500
3 BHK1,388 sq ft₹1.04 croreabout ₹7,490
3 BHK1,447 sq ft₹1.08 croreabout ₹7,460
3 BHK1,732 sq ft₹1.29 croreabout ₹7,450

Other portals do not agree. Homes247 shows “price on request” with no sizes. Treat every figure here as an asking price, not a final deal.

Floor plan of a 2 BHK flat of 1,147 sq ft with drawing-dining room, two bedrooms, kitchen and balconies
2 BHK, 1,147 sq ft super built-up. Plan as shown on the Houssed listing.
Floor plan of a 3 BHK flat of 1,732 sq ft with drawing room, dining, three bedrooms and two toilets
3 BHK, 1,732 sq ft super built-up. Plan as shown on the Houssed listing.

Amenities check: Houssed lists a clubhouse, gym, kids’ pool, jogging track and more. The RERA filing lists none of these, and the plot is only 0.34 acre. The amenity picture on that listing is a stock playground image whose file name refers to a different project’s brochure.

🔍 Jasoos take: Only what is written in your agreement for sale counts. Ask for the amenity list and the carpet area (not just super built-up) in writing.


6. Complaints, cases and buyer reviews

  • RERA cases: none found. We searched the full Bihar RERA proceedings list (about 10,900 entries), the adjudicating officer’s orders and the defaulter list for “Grihini” and “Lilaravi”.
  • News and court reports: none found.
  • Social media: we found no posts about this project or builder on Reddit (r/patna, r/bihar), X, Facebook or YouTube, and no buyer reviews on portals.
  • Construction progress: RERA quarterly progress reports were not visible on the public page, so we could not confirm how far work has got.
Timeline from firm registration in February 2022 to the RERA completion deadline of 19 May 2028
Chart: PropertyJasoos, from the Bihar RERA filing.

7. Buyer checklist before booking

  • Get a copy of development agreement deed 9339 and the landowner’s title chain, and have a property lawyer check them.
  • Pay only into the RERA collection account, named “Grihini Homes-Lilaravi Enclave”, at IDBI Bank, Ashiana branch. Never pay in cash.
  • Confirm whether your flat is in the builder’s share (201 to 208, 301 to 308) or the landowner’s share.
  • Get the carpet area, amenity list, parking slot and possession date written into the agreement for sale.
  • Visit the site and photograph the progress, then visit again before each payment that is linked to construction progress.
  • Check that your bank has approved the project for a home loan.
  • Remember that the building permit and the RERA registration both end around May 2028. Ask the builder what happens if work runs late.

Sources

Checked on 22 October 2026. Details can change; verify on the RERA portal before you pay. If you are a buyer or the builder and have an update, write to us and we will add it.

Make the next step evidence-led

Reading about property is useful. Checking yours is better.