We are detectives for property, and we share what we investigate.
The 1.5 km road meant to connect Patna Sahib railway station directly to JP Ganga Path is still not finished, eight months after its original deadline. Chief Minister Samrat Choudhary inspected the work in Patna City on Saturday, 14 November 2026, and told officials to complete it on schedule without compromising on quality, according to ANI, UNI and Voice of Bihar. None of the reports gives a new completion date.
What the project is
| Detail | As reported |
|---|---|
| Route | Patna Sahib railway station to the Patna Ghat access point of JP Ganga Path (Marine Drive) |
| Length | About 1.5 km (Patna Press says 1.55 km) |
| Road | Four lanes, 30 m wide, with service lanes on both sides, built on a former railway corridor (Patna Press) |
| Cost | Rs 52.54 crore |
| Work started | 5 April 2025 |
| Original deadline | 12 months, by March 2026 (Prabhat Khabar) |
| Later estimate | July 2026 (Patna Press) |
| Extras | A flyover on Ashok Rajpath, and a road over bridge (ROB) at Patna Sahib station that links JP Ganga Path to the new NH-30 |
At the inspection, Road Construction Department Principal Secretary Pankaj Kumar Pal briefed the Chief Minister. Urban Development Secretary Animesh Parashar, Municipal Commissioner Yashpal Meena and Patna DM Kundan Kumar were also there, as The News Mill and Asianet Newsable reported.
How the deadline has slipped
Then Chief Minister Nitish Kumar started the work on 5 April 2025 (Amar Ujala). The contract period was 12 months, with completion targeted for March 2026, Prabhat Khabar reported. A later Patna Press report said the first phase, from JP Ganga Path to the roundabout near Patna Ghat, was already open to traffic, while the second phase (the overbridge and the approach road up to the station) was expected by July 2026. Work picked up after the railways handed the needed land to the state, according to the same report.
It is now mid-November and the station end is still under construction. The officials’ line this week was “within the scheduled time”, but no outlet reported what that time now is.
Why it matters
Officials say the link will give Patna Sahib station direct access to JP Ganga Path and take pressure off Ashok Rajpath and the Marufganj Mandi area, two of the most jammed stretches in Patna City. Once the ROB is built, traffic from the station side should also be able to reach the new NH-30 without going through the old city lanes.
π Jasoos take
If you are looking at a flat in Patna City, Gulzarbagh or along Ashok Rajpath east of Gandhi Maidan, you may hear that “Ganga Path is five minutes away”. From the station side, that is true only once this link and its ROB open. The project has already missed a March deadline and a July estimate, and the latest official word has no date at all.
Price the flat on the roads that work today. Treat the link road as a likely future bonus, not something to pay a premium for now. Also note that we found no updated cost figure: the Rs 52.54 crore number is the original one.
What to check
- Drive the route at office hours from the project gate to JP Ganga Path and to NH-30, and time it.
- If a brochure promises Ganga Path access, ask which approach it means: the open Patna Ghat roundabout section, or the unfinished station end.
- Check whether the project sits close to the new flyover or ROB. Construction dust and diversions can last months, and an elevated road next to a balcony changes noise and light.
- Ask the builder to put any “connectivity” claim in writing, not just in an ad.
Sources
- ANI: Complete Patna Sahib-Patna Ghat link road within deadline, CM tells officials (14 Nov 2026)
- UNI: Bihar CM directs timely completion of Patna Sahib link road
- The News Mill: CM directs timely completion of Patna Sahib link road
- Asianet Newsable: Bihar CM inspects Patna Sahib station link road
- Voice of Bihar: Rs 52.54 crore link road inspection (Hindi)
- Prabhat Khabar: Link road to be built by March 2026 (Hindi)
- Patna Press: Patna Sahib to JP Ganga Path connectivity by July 2026
- Amar Ujala: Work starts on Patna Sahib to Patna Ghat link road (5 Apr 2025, Hindi)