The Patna High Court has ruled that the Real Estate Regulatory Authority, Bihar (Bihar RERA) cannot ask a builder for documents that the law does not list, and that a project application left undecided for more than 30 days becomes registered on its own. In a judgment dated 5 November 2026 in Aditya Niwas Developers and Colonizers v. State of Bihar (CWJC No. 5406 of 2026), Justice Ajit Kumar declared the developer’s residential project “Chhabilchandra Enclave” deemed registered and told Bihar RERA to issue its registration number, login ID and password, as reported by LiveLaw Biz. The judgment text is on Indian Kanoon.
How the case unfolded
| When | What happened |
|---|---|
| June 2025 | Aditya Niwas applies to Bihar RERA to register Chhabilchandra Enclave (the judgment text gives 9 June 2025; LiveLaw Biz reports 19 June 2025) |
| 30 days later | The statutory window for RERA to grant or reject the application passes with no decision |
| 18 December 2025 | RERA issues a notice proposing to reject the application because three documents are missing |
| 8 January 2026 | RERA passes an order in the matter |
| 16 February 2026 | RERA rejects the application |
| 5 November 2026 | High Court quashes the notice, the order and the rejection, and declares the project deemed registered |
What the court said
The rule is in Section 5 of the Real Estate (Regulation and Development) Act, 2016. RERA has 30 days from receiving an application to either grant registration or reject it with reasons. If it does neither, Section 5(2) says the project is deemed registered, and RERA must then give the promoter a registration number and login details.
The court made three points, according to LiveLaw Biz and the judgment:
- Only the listed documents. The documents a promoter must file are set out in Section 4 of the Act and Rule 3 of the Bihar RERA Rules, 2017. The three documents RERA asked for were not among them. Letting RERA demand more would widen its powers beyond what the legislature gave it.
- The clock does not restart. The 30 days run from receipt of the application. Raising queries does not reset them.
- Deemed registration is final. Once the period lapsed, the project was registered by operation of law, and a later rejection could not undo that, even though the builder had asked for more time to file the papers.
The reports do not name the three documents RERA wanted, and do not give the project’s location or size. We found no report of an appeal or a stay so far.
π Jasoos take
For buyers, this ruling cuts both ways.
The good side: builders cannot be held up for months by open-ended paperwork demands. A project that files the documents the law lists should get an answer in 30 days, and delays at the registration stage often end up in the price or the handover date.
The side to watch: a deemed registration means the project got its RERA number because the clock ran out, not because RERA finished checking it. A RERA number tells you the project is allowed to be marketed and sold. It has never been a guarantee of clean land title or a valid building map, and in a deemed case you cannot even assume RERA raised its usual questions. Do that checking yourself.
Also watch for the mismatch this case creates. Chhabilchandra Enclave appeared on Bihar RERA’s list of rejected projects. If a builder shows you a project that the RERA website calls rejected but says it is registered, ask for the court order and check that RERA has actually issued the registration number.
What to check before booking
- Search the project on Bihar RERA’s registered projects page and note the registration number and its validity date.
- Open the uploaded documents: land title papers, the approved building plan and permit, and the development agreement if the land belongs to someone else. Our Lilaravi Enclave investigation shows how to read a Bihar RERA file.
- Ask the builder in writing how the project was registered. If the answer is “deemed registration” or “by court order”, get a copy of the order.
- Match the approved map number and the plot details in the RERA file with the sale agreement you are asked to sign.
- Check RERA’s complaints and orders pages for the builder’s name before paying a booking amount.
Sources
- LiveLaw Biz: Bihar RERA cannot demand documents beyond those prescribed by law for project registration (2026 LLBiz HC(PAT) 35)
- Indian Kanoon: Aditya Niwas Developers and Colonizers vs The State of Bihar, 5 November 2026
- LiveLaw Biz: RERA cases weekly digest, 1 to 7 November 2026
- Bihar RERA: rejected projects list